Arapahoe Avenue closed between 15th and 17th streets on Saturday
Aug 9th
Eastbound Arapahoe Avenue between 17th and Folsom streets will remain open, businesses along Arapahoe Avenue will remain open, and the Boulder Farmers’ Market will remain at its current location. Travelers are encouraged to walk or bike along the Boulder Creek Path, ride buses, or use Canyon Boulevard and the downtown parking garages if driving.
The one-day full closure between 15th and 17th streets is a final step in the first phase of the Arapahoe Avenue Reconstruction project. Phase two is scheduled to begin on Saturday, Aug. 17, when westbound Arapahoe Avenue will be reopened to traffic, and will continue through May 2014. During phase two of the reconstruction, Arapahoe Avenue will have intermittent daytime lane closures; travel in both directions will remain open throughout. The JUMP bus will remain on Arapahoe Avenue, but there may be temporary bus stop closures. Phase two includes irrigation relocation and construction of curbs, gutters, driveways, and sidewalks.
By fall 2014, Arapahoe Avenue will be reconstructed into concrete between Folsom and 15th streets, along with additional enhancements. For more information, call 303-441-3266 or visit www.bouldertransportation.net and select “Arapahoe Avenue Reconstruction.”
To receive email updates about construction project locations and schedules, visit the City of Boulder Email Listspage and select “Public Works News.” For the latest construction traffic information, visitwww.boulderconezones.net and follow @boulderconezone on Twitter.
— CITY —
Summer nightmare on Arapahoe between Folsom and 17th
Feb 24th
The City of Boulder invites the community to an open-house meeting for the upcoming Arapahoe Avenue Reconstruction project on Monday, Feb. 25, from 5 to 6:30 p.m. in the Creekside Room at the West Senior Center, 909 Arapahoe Ave. Please attend the meeting to learn more about the proposed transportation improvements and the anticipated construction timeline, traffic impacts, and detours associated with the project.
Arapahoe Avenue, between Folsom Street and approximately 17th Street, is in poor condition and in need of a reconstruction. The proposed improvements include:
• reconstructing Arapahoe Avenue into concrete between Folsom and 17th streets, and potentially
continuing to 15th Street, as funding allows;
• reconstructing deteriorated sidewalks and driveways, installing ADA-compliant curb ramps, and
widening sidewalks, where space allows;
• extension of the student-drop off area and multi-use path on the south side of Arapahoe Avenue
along the Boulder High School property;
• improving underground utilities and installing storm sewers; and
• improving urban design, landscaping and transit stops, as funding allows.
The reconstruction is planned to begin in late May 2013 and will be completed in fall 2013. The project is funded by the 2011 voter-approved Capital Improvement Bond, which allowed the city to leverage existing revenues to bond for approximately $49 million to fund projects that address significant deficiencies, such as this one, and high priority infrastructure improvements.